Apac data centre capacity to double by 2030, AI boom creating ‘generational shift’ in power demand: JLL
The AI and data centre boom has actually led to a “generational shift in power need”, stated Steven Jack, the business’s head of energy and infrastructure for Europe, the Middle East and Africa, in a Sept 8 release. “Utilities that were figuring moderate growth are currently grappling with numbers almost multiply their previous price quotes.”
Data facility capacity in Asia Pacific (Apac) is predicted to nearly double by 2020, as AI-fuelled growth turns around a decades-long pattern of steady or declining electricity need, according to study by JLL.
While data centre build-out still outpaces grid planning in a number of Apac markets, Cameron expects regional characteristics and grid access challenges to drive brand-new partnership designs. “Whilst the solution will differ relying on circumstances, it is clear we will see a lot more collaboration possibilities and innovative solutions in between data centre and power customers across the area.”
Subsequently, grid access is increasingly driving decision-making for developers, data centre drivers, energy firms, and tech business. “For any energy developer, without having a grid link, you do not have a project,” Jack explained. “For financiers, this grid congestion translates straight right into threat, however it also develops a scarcity costs for possessions that provide or obtain grid accessibility.”
In any case, safeguarding power supply is now leading of mind for data center investors in Apac, claimed James Cameron, JLL’s head of energy and facilities for the area. “In liberalised industry in Apac, such as Australia, India, Japan and the Philippines, status and place of grid link is the very first inquiry for financiers and has the biggest assessment impact for development assets.”
Data compiled by the property consultancy shows that Apac information center capacity will jump from 32 gigawatts (GW) to 57 GW by 2030. Globally, data center capacity is anticipated to hit 200GW already, driven mainly by hyperscale cloud expansion and AI demand.
In the middle of a decentralised influx of brand-new renewable energy sources, presenting transmission facilities– initially created for large, centralised power stations– has struggled to cope, resulting in considerable grid congestion around the world.
That shift has actually emphatically reshaped the data center landscape, with grid infrastructure now emerging as the key restriction. “Power need is rising much faster than grids were built to handle,” commented Matt Eastwick, JLL’s US group head and senior regulating director for energy and facilities.
The restrictions are developing new possibilities in associated industry. One such chance hinges on battery energy storage systems (BESS), which JLL posits will play a significantly important role in handling restricted grid access and renewable resource intermittency. “They act as shock shields for constricted grids, billing when power is low-priced and plenty, then discharging when need and cost are high,” stated Eastwick.
Against this backdrop, hyperscalers have disclosed US$ 200 billion ($ 253 billion) in infrastructure costs for 2026, up 51% from 2025. Nonetheless, despite the document capital investment, interconnection queues for brand-new sustainable projects now extend to 4 years or even more in some regions, with certain areas compelled to pause brand-new connections completely, according to JLL.
At the same time, grid access obstacles are prompting sector gamers to turn into straight players in the energy market, with some technology companies opting to straight up purchase operating renewable assets to assure energy source, according to JLL.